Operator Avoided Regulatory issues by staying within Boundaries

Operator Avoided Regulatory issues by staying within Boundaries

Operator Avoided Regulatory issues by staying within Boundaries

Hard Line Alerts help proactively stay within boundaries

While focusing on performance on a constrained site directional driller crossed the lease boundary. This created several days of unnecessary workload and paperwork for the team as well as missing perforation zones contributing to reduced production.



Key Results & Value Delivered

AI Driller Hard Line Alerts were enabled for drilling engineers, directional drillers, and wellsite leaders to proactively streamline communication and prevent re-occurrence. The entire pad was delivered 14 days ahead of schedule while all the wells stayed within 25m from the boundary. Hard Line Alerts became the best practice and part of the new workflow for the Operator to ensure regulatory compliance and operational consistency.


Western Canada

Region

Montney

Field / Basin

0 days

Ahead of Schedule

14 days

Ahead of Schedule